Immokalee Downtown Stormwater Improvements

immokalee-downtown-stormwater-improvements-image1
The purpose of this project was to develop construction plans and contract documents for construction of the Downtown Immokalee elements of the Immokalee Stormwater Management Master Plan. Agnoli, Barber & Brundage produced the construction plans as sub-consultant to CDM Smith, which was the prime consultant for the project. ABB successfully completed the plans and contract documents for the improvements to the 110 Acre +/- developed area consisting of approximately 17,700 feet of storm sewer construction including 262 feet of 4’ x 6’ box culverts. The plans were completed within the very tight schedule as required by the Immokalee CRA’s construction grant. The project was also competed within budget as evidenced by a close-out change order resulting in the project being $8,200 under budget.